Bangladesh Switches On Its First Nuclear Power Plant as Rooppur Feeds Electricity to the National Grid
Bangladesh has switched on nuclear power for the first time in its history. On Tuesday 17 November 2026, the first unit of the Rooppur Nuclear Power Plant began feeding electricity into the national grid on a trial basis, supplying up to 350 megawatts (MW) in its first hours. The milestone makes Bangladesh the 33rd country in the world to generate electricity from nuclear power — the result of a dream first proposed more than six decades ago.
The moment came at 3:16pm local time, when engineers synchronised the plant’s first reactor with the national transmission network. Science and Technology Minister Fakir Mahbub Anam was present at the plant in Ishwardi, in the Pabna district, to witness the connection. “This is a historic achievement,” he said.
But officials were quick to add a note of caution: this is a test, not the start of everyday commercial supply. The plant must now pass months of technical trials and regulatory checks before it can deliver electricity at full capacity on a permanent basis.
What happened on 17 November
The first grid connection, known in the industry as “first grid synchronisation”, is a carefully planned test. The unit initially supplied up to 350MW to the grid, before output was reduced to 300MW to keep the national grid stable, according to the science and technology ministry.
The initial connection was scheduled to last around eight to 10 hours. The unit would then be disconnected for further tests, and reconnected after a break of about 28 hours to supply electricity for another four to six hours, project director Md Kabir Hossain told The Daily Star.
During these tests, engineers will check how the reactor, turbine, generator and control systems perform together, and how the plant’s electricity interacts with the national grid. Output will be raised or lowered, and the unit may be switched off and on repeatedly as the testing continues.
Electricity generated during the trial period can be used by consumers, but an uninterrupted supply cannot yet be guaranteed. Power Grid Bangladesh PLC will manage the balance of the grid, while the Bangladesh Power Development Board (BPDB) will monitor the supply.
“This is a historic achievement,” Minister Fakir Mahbub Anam said at the plant. “The first grid synchronisation was successful and the national grid remained stable,” added BPDB Member (Generation) Md Zahurul Islam, who said the grid had been prepared to receive electricity from Rooppur and that the extra supply would help meet rising demand.
A 65-year wait: the long road to Rooppur
For Bangladesh, this moment has been a very long time coming. The idea of building a nuclear power plant in the country dates back to 1961, when the proposal was first made. Rooppur, on the banks of the Padma River, was selected as the site in 1963. But for decades, the project stayed on paper.
Here is how the journey unfolded:
- 1961–65: Plans for a nuclear power plant are initiated, and Rooppur in Pabna is selected as the site.
- 1973: The Bangladesh Atomic Energy Commission (BAEC) is formed.
- 1977–80: A feasibility study finds the project viable, but efforts to secure financing fail.
- 1987–88: German and Swiss firms carry out another feasibility study.
- 1993–2000: A nuclear safety law is enacted, and the government decides in principle to go ahead with the project.
- 2010: Parliament approves the country’s first nuclear power project.
- 2011: Bangladesh and Russia sign an agreement to build a two-unit plant.
- 2013: The foundation stone is laid at Rooppur.
- 2015–16: The construction contract and project financing agreement are signed with Russia.
- 2017: Construction of the first unit begins in November.
- 2023: The first batch of nuclear fuel arrives at the plant.
- 16 April 2026: Unit 1 receives its commissioning licence from the regulator.
- 28 April 2026: Fuel loading begins at Unit 1.
- October 2026: The reactor reaches its first criticality — the point where the nuclear chain reaction becomes self-sustaining.
- 17 November 2026: Unit 1 connects to the national grid for the first time, supplying up to 350MW on a trial basis.
For people living near the plant, the grid connection felt deeply personal. Amirul Islam, a 65-year-old retired schoolteacher from Rooppur village, told The Daily Star that he had heard talk of a nuclear power plant since childhood. “Since my childhood, I have been hearing that a nuclear power plant would be established here in Rooppur. We had a dream of seeing the plant become a reality. Now that dream has come true as the plant has started feeding electricity into the national grid,” he said. “As residents of the area around the nuclear plant, we feel proud. Now our demand is uninterrupted electricity supply at an affordable rate.”
Md Mojnu, a tea-stall vendor in the area, said local people had at first been worried about the plant because of fears surrounding nuclear energy. “We have overcome our fear of the nuclear plant. Now we feel proud of it,” he said, adding that the project had transformed the locality.
What is the Rooppur plant?
The Rooppur Nuclear Power Plant is Bangladesh’s first nuclear power station and the largest single project in the country’s history. It is being built by the Bangladesh Atomic Energy Commission, with Atomstroyexport — a subsidiary of the Russian state-owned nuclear corporation Rosatom — as the contractor.
The plant has two VVER-1200 reactors, each with a gross generation capacity of 1,200MW. Together, the two units will be able to generate 2,400MW of electricity. The VVER-1200 is a third-generation pressurised water reactor design, the same type Russia has supplied to several other countries.
The plant stands at Rooppur in Ishwardi Upazila, on the bank of the Padma River, about 160 kilometres northwest of the capital, Dhaka. Its four cooling towers, each about 175 metres high, now dominate the skyline beside the historic Hardinge Railway Bridge and the Lalon Shah Road Bridge.
While Unit 1 has entered the grid-synchronisation and testing phase, construction of Unit 2 is still underway. The safety review by the International Atomic Energy Agency (IAEA) was successfully completed in late 2025.
Russia’s role as a builder of nuclear plants abroad is growing. Moscow has also agreed to support new nuclear projects in other countries, including a 2,000 MW nuclear plant in Ghana, as governments look for large-scale, low-carbon sources of electricity.
Why this matters for Bangladesh
Bangladesh has about 170 million people, and its demand for electricity keeps growing as the economy expands and more homes, factories and businesses connect to the grid. But the country’s power system still depends heavily on natural gas, imported coal and furnace oil — fuels whose prices swing sharply on world markets and which must largely be bought with scarce foreign currency.
Nuclear power offers something different: a large, steady supply of electricity that does not depend on imported fuel shipments or the weather. Once both units are running at full capacity, the plant is expected to meet more than 10 percent of Bangladesh’s electricity demand, according to officials quoted by The Hindu.
That matters for a country that has struggled in recent years with power shortages, rising import bills and pressure on its foreign exchange reserves. A stable, home-grown source of base-load power — electricity that runs around the clock — could help factories keep running, keep lights on in homes, and reduce the need for expensive fuel imports.
The plant also changes Bangladesh’s place in the region. With India and Pakistan already generating nuclear electricity, Bangladesh now joins them as South Asia’s third nuclear-power producer, and the 33rd country in the world to do so.
The cost question
The milestone arrives alongside serious questions about money. The project cost has climbed to Tk 1.39 lakh crore, around Tk 26,000 crore above the previous estimate, partly because of the depreciation of the taka against the US dollar. Around 90 percent of the cost is being financed through a Russian state loan.
The price at which the power board will buy electricity from the plant has not yet been finalised. BPDB initially estimated a purchase price of Tk 6.72 per unit, but officials have indicated that it could rise to around Tk 10 after a review of construction, operation and maintenance costs. BPDB Chairman Rezaul Karim told The Daily Star that the board had sought detailed information on these costs before finalising the purchase price.
Construction has also run behind schedule. Building began in November 2017, with the original completion deadline set for December 2025. The deadline has been extended twice, most recently to June 2028.
These are real concerns, and they will shape how Bangladeshis judge the project in the years ahead. A plant that produces expensive electricity, or one that takes far longer to finish than planned, delivers less value to the people paying for it. But for now, the government and the plant’s supporters point to the grid connection as proof that the long-delayed project is finally delivering power.
What happens next
The hard work is far from over. Under the agreement with the Russian contractor, Unit 1 must undergo a 10-month trial operation before it can begin permanent commercial electricity supply at full capacity. The World Nuclear Association’s World Nuclear News reports the same timeline, noting that the trial period must be completed in collaboration with Russia before regular commercial supply begins.
Before the next phase of trial operation can start, the plant needs approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA), the country’s nuclear regulator. Generation will then be increased gradually towards the unit’s full capacity of 1,200MW, a process that could take several months.
Minister Anam expressed hope that the unit would reach full capacity by late January or early February next year. That would not necessarily mean the start of permanent commercial operation, however, since the 10-month trial must still run its course.
After the trial, the contractor is expected to provisionally hand over the unit to the Bangladesh Atomic Energy Commission. The Nuclear Power Plant Company Bangladesh Limited (NPCBL) will then operate the plant as its designated operating organisation, subject to the required government notification.
Meanwhile, construction of Unit 2 continues, and the full 2,400MW capacity of the plant is still some way off.
Nuclear power and the questions ahead
Nuclear power divides opinion around the world. Supporters point out that it produces large amounts of electricity without the carbon emissions of coal, gas or oil, and that it can run steadily day and night, unlike solar and wind power. The technology is even expanding into new frontiers — the US, Russia and China are racing to put nuclear reactors on the Moon. Critics raise concerns about safety, the cost of building plants, and the problem of storing radioactive waste for thousands of years.
Bangladesh’s plant has been through the international safety system: the IAEA completed its safety review in late 2025, and BAERA must approve each step of the trial operation. The VVER-1200 design includes passive safety systems designed to keep the reactor safe even if power is lost, meeting safety standards strengthened after the Fukushima accident in Japan in 2011.
The debate over cost and safety will continue. But the grid connection on 17 November is a fact that cannot be undone: after 65 years of proposals, feasibility studies, delays and construction, nuclear electricity is now flowing — even if only in test quantities — into Bangladeshi homes and businesses.
Frequently asked questions
When did Bangladesh’s first nuclear power plant start supplying electricity?
Unit 1 of the Rooppur Nuclear Power Plant was connected to the national grid for the first time on Tuesday 17 November 2026, at 3:16pm local time. It supplied up to 350MW on a trial basis.
Is the Rooppur plant now in commercial operation?
No. The 17 November connection was a trial, not the start of commercial operation. Unit 1 must complete a 10-month trial operation and pass further regulatory checks before it can supply electricity commercially at full capacity.
How much electricity will Rooppur generate?
The plant has two reactors, each with a capacity of 1,200MW, giving a combined capacity of 2,400MW. Once fully operational, it is expected to meet more than 10 percent of Bangladesh’s electricity demand.
How much did the Rooppur plant cost?
The project cost has risen to Tk 1.39 lakh crore, around Tk 26,000 crore above the previous estimate. About 90 percent of the cost is financed through a Russian state loan. The electricity tariff has not yet been finalised.
Who built the Rooppur Nuclear Power Plant?
The plant is being built by the Bangladesh Atomic Energy Commission, with Atomstroyexport, a subsidiary of the Russian state nuclear corporation Rosatom, as the contractor. It uses Russian VVER-1200 reactor technology.
Where is the Rooppur plant located?
The plant stands at Rooppur in Ishwardi Upazila, in the Pabna district, on the bank of the Padma River, about 160 kilometres northwest of Dhaka.
Conclusion
Bangladesh’s first nuclear power plant has moved from a six-decade-old dream to a working reality. The 350MW that flowed into the national grid on 17 November 2026 was only a test, and months of trials, regulatory approvals and rising costs still lie ahead. But the grid connection marks a genuine turning point: Bangladesh has joined the small club of countries that generate electricity from the atom, and a new source of steady, large-scale power is now within reach. Whether Rooppur lives up to its promise will depend on what happens next — the trial operation, the final tariff, and the completion of the second unit. For now, the country can mark the day its nuclear era began.
Sources
- The Daily Star: “Atomic power flows into national grid”
- The Hindu: “Bangladesh connects first nuclear power plant to national grid”
- World Nuclear News: “Bangladesh’s Rooppur 1 supplies country’s first nuclear energy”
- Bangladesh Sangbad Sangstha (BSS): “Rooppur plant starts supplying electricity to national grid”
- Prothom Alo: “Nuclear power connected to national grid for the first time”
- Wikipedia: “Rooppur Nuclear Power Plant”